| Engine : Engineering Safety - 335/968 |
|---|
| « Previous Question |
| When discharging clean ballast, prior to entering the loading port, if the ballast is determined by the oil monitor to exceed 15 parts per million of oil, the deballasting must _________. |
| A) be terminated automatically |
| B) be completely discharged in order to load |
| C) be stopped until the oil can settle out, then resumed at a slower discharge rate |
| D) be completed only after "load on top" has been completed |
loading answer...
| Comments |
|---|
| There are no comments for this question. |