The initial tension set in the mooring system of a MODU establishes the __________ . |
A) maximum water depth at which drilling operations can be conducted |
B) distance the unit can be offset from the wellbore before the restoring forces oppose the environmental forces |
C) maximum time it will take to disconnect the riser package in the event of a storm |
D) minimum amount of ballast needed to keep the vessel at operating draft during normal drilling operations |