| Coast Guard Regulations (46 CFR Part 56) require that new fuel oil service piping between pumps and burners be subjected to __________. |
| A) spot radiographic examination of portions of the finished weld joints |
| B) a hydrostatic leak test to the design pressure specified by the Coast Guard |
| C) a hydrostatic test of 1.5 times the maximum allowable pressure but not less than 500 psi (3447 kPa) |
| D) a hydrostatic test of 1.25 times the maximum allowable pressure with the relief valves closed |