Engine : Steam Plants - 691/811 |
---|
« Previous Question |
Coast Guard Regulations (46 CFR Part 56) require that new fuel oil service piping between pumps and burners be subjected to __________. |
A) spot radiographic examination of portions of the finished weld joints |
B) a hydrostatic leak test to the design pressure specified by the Coast Guard |
C) a hydrostatic test of 1.5 times the maximum allowable pressure but not less than 500 psi (3447 kPa) |
D) a hydrostatic test of 1.25 times the maximum allowable pressure with the relief valves closed |