When preparing to hydrostatically test water-tube boilers, you should __________.
A) remove all inspection plates and manhole covers as required by the marine inspector
B) make arrangements for simultaneously testing main and auxiliary steam stops with water and steam pressure
C) have the boiler warmed to a temperature not exceeding 100°F (37.8°C)
D) fill the boiler with water not less than 70°F (21.1°C), nor more than 160°F (71.1°C)