Engine : Steam Plants - 532/811
Get a hint
« Previous Question
Proper lagging of a single-element feed water regulator is accomplished by applying the insulation material __________.
A) only as necessary to prevent possible injury
B) to the steam connection, but not water connection
C) to both connections, including finned areas
D) to the water connection, but not steam connection