Log In


Engine : Electricity - 1384/1386
Get a hint
« Previous Question
When performing an absence-of-voltage test before commencing repair work, at the minimum where must the absence-of-voltage test be performed?
A) At the main feeder circuit breaker
B) At the point of contact where the work will take place
C) At the load-side disconnect switch
D) At the source disconnect branch circuit breaker
loading answer...
Comments
There are no comments for this question.
0 0 0%

Study Mode
Answers Only
Options
Clear Score