In accordance with 46 CFR, Subchapter J (Electrical Engineering), each diesel engine driven generator prime mover must have an over speed device, independent of the normal operating governor. If in testing the over speed device, what should be the trip point setting in terms of rated speed?
A) not to exceed 10% above rated speed
B) not to exceed 15% above rated speed
C) not to exceed 20% above rated speed
D) not to exceed 25% above rated speed