When replacing a gasket in a six-bolt flanged joint, in what order should the bolts be tightened?
A) Install and tighten bolts in pairs which are opposite each other in the flange (1-4, 2-5, and 3-6).
B) Each bolt should be installed and tightened in consecutive order in the counter-clockwise direction.
C) Each bolt should be installed and tightened in consecutive order in the clockwise direction.
D) Install and tighten bolts 1, 3, 4, 2, 5, and 6, in that order.