As a result of a load or set point change, in addition to minimizing the maximum value of the error, what are the two additional objectives of a closed-loop control system?
A) The closed-loop control system should maximize the settling time and maximize the residual error.
B) The closed-loop control system should minimize the settling time and minimize the residual error.
C) The closed-loop control system should minimize the settling time and maximize the residual error.
D) The closed-loop control system should maximize the settling time and minimize the residual error.