Engine_2014 : Steam Plants - 1650/1951
Get a hint
« Previous Question
The jacking gear must be engaged as quickly as possible when securing the main turbines in order to __________ .
A) permit rapid cooling of the reduction gears
B) prevent uneven cooling of the turbine rotors
C) maintain a constant supply of lube oil to the main unit
D) prevent the stern tube bearing from overheating