| Engine_2014 : Steam Plants - 138/1951 |
|---|
| « Previous Question |
| After a boiler generating tube has been plugged, __________. |
| A) a hole should be made in the defective tube |
| B) the firing rate should be reduced |
| C) the steam flow rate must be increased |
| D) all of the above |